- 800 VDC power architecture
- A rack power-distribution approach that replaces multiple AC conversion stages with a single high-voltage direct-current bus feeding the rack. It is promoted for multi-hundred-kilowatt AI racks to cut conversion losses and copper mass; standards are still forming.
- ASHRAE thermal guidelines
- The de facto environmental envelope for IT equipment. The fifth edition defines air-cooled classes A1–A4 — A4 permitting inlet air up to 40 °C — plus liquid-cooling classes named by maximum facility water temperature.[6]
- Battery energy storage system (BESS)
- Utility-scale batteries co-located with a facility to ride through disturbances, shave peaks, or sell flexibility to the grid. An NREL demonstration dispatched a 35 MW battery at a 70 MW grid-interactive data center in under five seconds without breaking service commitments.[11]
- Behind-the-meter (BTM)
- Generation or storage connected on the customer side of the utility meter, serving local load without waiting on grid-connection studies. BTM power is one route around long interconnection queues; the deployment overview covers how it pairs with modular capacity.
- CDU (coolant distribution unit)
- A pump-and-heat-exchanger skid that isolates the facility water loop from the technology cooling loop serving cold plates. It regulates flow, pressure, and supply temperature — typically holding coolant above dew point so condensation never forms on hardware.
- Closed-loop liquid cooling
- A cooling architecture in which a fixed charge of coolant circulates continuously between heat sources and heat rejection, with no evaporation and no continuous make-up water. Closed loops are what make zero-water operation and practical heat recovery possible.
- Cold plate
- A metal plate with internal fluid channels mounted directly on a processor package, moving heat into liquid at the die instead of into room air. The Open Compute Project publishes cold-plate requirements so plates, manifolds, and CDUs from different vendors interoperate.[9]
- Colocation
- Renting space, power, and cooling for your own hardware inside a shared third-party facility. Colocation transfers the facility problem to a landlord; available density and liquid-cooling readiness vary widely between sites.
- Demand response
- Utility or market programs that compensate large electricity consumers for reducing or shifting load during grid stress. A flexible data center can treat demand response as a revenue stream rather than an interruption.
- Direct-to-chip (D2C) liquid cooling
- A liquid-cooling method that pipes coolant through cold plates mounted on GPUs and CPUs, removing most heat at the silicon. Loop architecture and trade-offs are covered in the direct-to-chip liquid cooling explainer.
- Dry cooler
- A closed-circuit, air-to-liquid heat exchanger that rejects loop heat to ambient air without evaporating water. Dry coolers enable zero-water heat rejection at the cost of efficiency in peak heat.
- Edge data center
- A small facility placed near where data is generated or consumed, cutting latency and backhaul cost. AI inference is pushing edge sites from closet scale toward megawatt-class units; see the designed-for use cases.
- Energy reuse effectiveness (ERE)
- (Total facility energy − energy reused elsewhere) ÷ IT energy. Unlike PUE, ERE credits heat exported to buildings or processes, so it can fall below 1.0 for a facility with a real heat customer.
- Evaporative cooling
- Heat rejection that cools air or water by evaporating water, trading water consumption for electrical efficiency. It is the main driver of data-center water use and of WUE differences between designs.
- Facility water system (FWS)
- The building-side hydronic loop carrying heat from CDUs out to heat rejection — dry coolers, cooling towers, or a heat-reuse customer. Its supply temperature largely determines which rejection options are viable.
- GPU cluster
- A set of GPU servers linked by high-bandwidth fabric so thousands of chips behave as one machine. Density is rising fast: NVIDIA’s GB200 NVL72 places 72 GPUs and 36 CPUs in a single liquid-cooled rack acting as one NVLink domain.[7]
- Heat reuse (waste-heat recovery)
- Capturing heat a facility would otherwise reject and delivering it to a productive use — district heating, offices, industrial processes. NREL’s ESIF facility heats its office space with HPC waste heat and reports a PUE near 1.04.[8]
- Hyperscale data center
- A facility class operated by the largest cloud and AI platforms, typically tens to hundreds of megawatts with custom hardware and leading efficiency. Google reports a fleet-wide trailing-twelve-month PUE of 1.09 per its latest reporting.[2]
- Immersion cooling
- Liquid cooling that submerges entire servers in a non-conductive dielectric fluid, in single-phase or two-phase variants. It removes nearly all heat to liquid but changes serviceability and hardware qualification.
- Inference
- Running a trained model to produce output. Inference is latency-sensitive and often memory-bound, and over a model’s life it usually consumes more total compute than the training run did.
- Interconnection queue
- The ordered backlog of projects waiting on utility studies and network upgrades before they may connect to the grid. Queue timelines run to years in many regions, making grid access a defining constraint on where new AI capacity can be built.
- IT load
- The electrical power consumed by computing, storage, and network equipment alone — excluding cooling, conversion losses, and building systems. IT load is the denominator in PUE, WUE, and ERE.
- KV cache
- In transformer inference, the per-token key and value tensors held in GPU memory so earlier context is not recomputed. KV caches grow with context length and batch size; published research shows quantization to roughly 3.5 bits per channel can be quality-neutral.[10] The Syntropic overview covers the software side of memory efficiency.
- Medium-voltage (MV) switchgear
- Switching, protection, and metering equipment operating at medium voltage — roughly 1 kV to 35 kV, with 13.8 kV a common North American distribution class. How a site accepts and steps down MV power is covered in data-center power architecture.
- Microgrid
- A local energy system — generation, storage, and controls — that can run connected to the utility grid or islanded from it. Microgrids let compute operate where grid service is weak, delayed, or absent.
- Modular data center
- Data-center capacity produced as a factory-built, transportable unit — structure, power, cooling, and racks integrated and tested before shipment — rather than constructed in place. PODOS applies the model at fixed scale: each PODOS Pod is designed as a standardized 1 MW building block. For the full decision framework, see modular vs traditional data centers.
- N+1 redundancy
- A redundancy scheme providing one spare unit beyond the number required to carry the load — five pumps where four suffice. Contrast 2N, which duplicates the entire system, and N, which carries no spare at all.
- Open Compute Project (OCP)
- An industry body that open-sources data-center hardware and cooling specifications, including cold-plate, immersion, and CDU requirements. Its cooling-environments work is what keeps the liquid-cooling ecosystem multi-vendor.[9]
- Organic Rankine cycle (ORC)
- A heat engine that generates electricity from low-temperature heat by boiling an organic working fluid instead of water. ORC systems are one route to converting data-center waste heat into usable power rather than venting it.
- Power distribution unit (PDU)
- Equipment that takes conditioned facility power and distributes it to racks. PDUs are usually where circuit-level power monitoring lives.
- Power usage effectiveness (PUE)
- Total facility energy ÷ IT energy — the industry’s standard overhead metric, where 1.0 would mean zero overhead. Industry-average PUE has stayed roughly flat for about six years in Uptime Institute’s surveys,[1] while leading hyperscale fleets report figures near 1.09.[2]
- Rack density
- The power drawn by a single rack, in kW. Uptime’s 2025 survey shows densities climbing into the 10–30 kW band for many operators;[1] current AI racks sit far above that, which is why liquid cooling is displacing air.
- Rear-door heat exchanger (RDHx)
- A liquid-cooled coil that replaces a rack’s rear door, absorbing server exhaust heat into water before it enters the room. A retrofit-friendly middle step between air cooling and direct-to-chip.
- Substation
- The transformers and switchgear that step transmission or distribution voltage down for site use. For large campuses a new substation is often the longest-lead physical asset on the project.
- Technology cooling system (TCS)
- The server-side loop between the CDU and the cold plates, running treated coolant at controlled temperature and pressure — kept separate from the facility loop to protect hardware from water-quality excursions.
- Time-to-power
- The elapsed time from committing to a site until it can draw its contracted power — driven by interconnection studies, substation work, and utility construction. PODOS targets a 90-day window from order to commissioning for a standard unit, a target that presumes power is already available at the site; see how deployment is sequenced.
- Training
- Building or updating a model’s weights by processing large datasets across many synchronized GPUs. Training is throughput-bound rather than latency-bound, and it stresses interconnect bandwidth and sustained power draw.
- Uninterruptible power supply (UPS)
- Batteries or flywheels plus power electronics that carry the IT load for the seconds-to-minutes between a grid disturbance and generator pickup. UPS topology is a core decision in power architecture.
- Water usage effectiveness (WUE)
- Liters of water consumed on site per kWh of IT energy. Microsoft reports a design WUE of 0.30 L/kWh for new builds, down from 0.49 in 2021;[3] closed-loop designs aim for zero operational water consumption.
- Zero-water cooling
- Heat rejection designed to consume no water in operation — typically a closed coolant loop rejecting heat through dry coolers. It removes water permits and drought exposure from siting decisions.