Site & power readiness
Confirm power, permits, ground, access, and network before anything is specified. Read stage 01.
INSIGHTDeploy · Stage 04 · Transport & placement
Transport and placement is a freight-and-rigging problem, not a construction one. A finished unit is surveyed against the route, engineered as a load, permitted in every jurisdiction it crosses, delivered to a pad that is already finished, then rigged, set, and connected. Almost everything that decides this stage is settled weeks earlier — in the route survey and the interface drawing — not on lift day.
PUBLISHED LAST VERIFIED BY JOSEF ELIMELECHREVIEWED PODOS AI ENGINEERING
What this stage delivers
This stage is stage 04 of the six-stage deployment model. It begins while the unit is still on the factory line and ends the moment the interfaces are landed and commissioning can start.
Width, weight and height limits shape the enclosure before the factory cuts steel. Step outside them and permits, escorts and curfew windows follow.
State-issued oversize movement permits and building-code acceptance of factory-built work are separate processes. Both carry lead times.
It is the only part genuinely built on site, and the usual source of delay. Unfinished on arrival, the unit is stored rather than set.
Deployment model
Each stage hands a defined artefact to the next. Stage 04 receives a unit that has passed factory acceptance testing, and hands over a unit that is set, anchored, and mechanically connected.
Confirm power, permits, ground, access, and network before anything is specified. Read stage 01.
Fix the build specification from a bounded menu, then freeze it. Read stage 02.
Assembly, integration, and burn-in on the line, ending in a factory acceptance test. Read stage 03.
Ship as heavy freight, rig, set, and connect. It ends with the unit set and mechanically connected.
Energize, verify, and load-test on site power until the site acceptance test passes. Read stage 05.
Monitor, maintain, and grow unit by unit once the schedule stops. Read stage 06.
TP-01 → TP-07
Seven steps, in order, with the item that actually carries the risk in each.
| Step | Activity | What it covers | Where the risk sits |
|---|---|---|---|
| TP-01 | Route survey | Drive the route from the factory gate to the pad: bridge ratings, overhead clearances, turning radii, weight-restricted roads, seasonal restrictions. | The survey — not the lift — is where placement projects succeed or fail. |
| TP-02 | Load engineering | Fix transport configuration, tie-down and lift points, centre of gravity, and the trailer type the envelope demands. | Determines which permits are needed and whether a crane or transporter sets the unit. |
| TP-03 | Permits and escorts | Apply per jurisdiction for oversize/overweight movement; add pilot vehicles, police escorts, or curfew windows where required. | Permits are issued state by state and carry lead times that belong on the critical path. |
| TP-04 | Pad and interface readiness | Complete pad, anchors, conduit stub-ups, heat-rejection clearance and network handoff before the unit ships. | An unfinished pad converts a delivery into paid storage. |
| TP-05 | Delivery and staging | Arrive, stage the trailer, establish the exclusion zone, set crane mats or transporter path, hold the pre-lift briefing. | Ground bearing pressure under the crane matters as much as under the unit. |
| TP-06 | Rig and set | Lift under an engineered plan with rated rigging and spreader geometry; land on anchors; confirm level and alignment. | Wind limits govern; a marginal forecast stops the lift, not the schedule discussion. |
| TP-07 | Interface connection | Terminate power, connect heat-rejection and any facility fluid interfaces, land fibre, verify grounding and bonding. | The interface list is the acceptance boundary between logistics and commissioning. |
Design constraint
A modular unit is designed backwards from the road. Federal standards fix vehicle width on the National Network at 102 inches — a figure no state may set higher or lower — and cap Interstate System weights at 20,000 lb on a single axle, 34,000 lb on a tandem axle, and 80,000 lb gross vehicle weight. Vehicle height is deliberately left to the states, so the legal ceiling changes as the route crosses borders.[1] Anything outside those figures moves as an oversize or overweight load under a permit issued by each jurisdiction, not by a single national authority.
That is why the envelope is a design input rather than a shipping detail. An enclosure that stays inside the routine legal envelope travels on standard trailers, on ordinary notice, with no escort. One that steps outside it acquires permits, pilot vehicles, curfew windows, and — on some corridors — seasonal weight restrictions that close the route for part of the year. Where the enclosure is built to ISO Series 1 corner-fitting geometry, standard container handling gear and twistlocks apply, because those dimensions and ratings are internationally standardized.[3]
Two tracks
Two permit tracks run in parallel and are frequently confused. The first is transport: state-issued oversize and overweight movement permits, applied for per jurisdiction, with lead times that belong on the critical path rather than in a logistics footnote. The second is the building-code track — the authority having jurisdiction still has to accept a structure that was largely built somewhere else.
The off-site construction standards ICC/MBI 1200 and 1205 exist precisely for that handoff. They set out how compliance is demonstrated when fabrication happens in a plant: in-plant inspection, third-party inspection agencies, state industrialized building programs, and a final on-site inspection covering the work that could only happen at the site.[2] Understanding that division early is what keeps site inspection scoped to foundations, connections, and setting instead of re-litigating factory assembly at the pad.
The one thing built on site
The pad is the one part of a modular deployment that is genuinely built on site, and it is the most common source of delay. Every item below should be complete and verified before the transport leaves the factory — not scheduled to finish while it is in transit. For the wider site picture, work through the data center readiness checklist.
Two site facts deserve attention beyond the checklist. Because the unit stands outdoors, its enclosure rating is a siting constraint: IP codes describe protection against solids and liquids, NEMA enclosure types add corrosion, icing, and construction requirements, and the two systems are not interchangeable in either direction.[4][5]And heat-rejection equipment is sized against the specific pad's design conditions — the design dry bulb and coincident wet bulb published for the nearest climatic station, not a national average.[6] Both belong in the enclosure and thermal design conversation before the pad is poured.
Hold points
Eight acceptance criteria. Each one is a hold point: unmet, it stops the transport rather than the lift.
| Ref | Hold point | Acceptance criterion — verified before the transport leaves the factory |
|---|---|---|
| PR-01 | Pad | Pad is level, load-rated, and drained, with documented bearing capacity for both the unit and the placement equipment. |
| PR-02 | Anchorage | Anchorage or tie-down provisions are installed and located to the unit's published interface drawing, not improvised on the day. |
| PR-03 | Stub-ups | Conduit and service stub-ups terminate where the unit's connection points will land, with slack for final alignment. |
| PR-04 | Heat-rejection clearance | Clearance around heat-rejection equipment is preserved — no walls, fences, or neighbouring plant inside the airflow envelope. |
| PR-05 | Placement standing area | Crane standing area or transporter path is prepared: mats sized, underground services located, overhead lines cleared or de-energised. |
| PR-06 | Site access | Site access from the public road carries the transport load — culverts, turning radii, gate widths, and any temporary road works. |
| PR-07 | Network handoff | Network handoff point is installed and tested to the demarcation, so fibre termination is a connection rather than a build. |
| PR-08 | Documents | Permits, insurance certificates, and the lift plan are on site and current before the transport leaves the factory. |
Lift day
A mobile crane is the default because it is quick where access allows, but the lift is an engineered operation: a written lift plan, rated rigging matched to the unit's designated pick points, spreader geometry that keeps sling angles inside their rating, mats sized to the crane's ground bearing pressure, a located-and-cleared underground and overhead survey, an exclusion zone, and a wind limit that stops work regardless of what the schedule says.
Where a crane cannot stand — constrained yards, overhead lines that cannot be de-energised, poor ground, or a pad tucked behind an existing building — the load is placed by self-propelled modular transporter, jack-and-slide, or roller sets. Those methods trade speed for reach and change what the site must provide: a continuous prepared path rather than a single standing area. That choice belongs in the route survey, because it changes the pad design.
Connection follows setting. Power terminations are field work governed by the electrical code in force at the site[7] and executed against the power architecture defined during configuration; heat-rejection and any facility fluid interfaces are made up and pressure-checked; fibre is landed at the demarcation. When the interface list is signed off, the unit passes from logistics to commissioning.
In the product
PODOS treats the road as a design constraint rather than a downstream problem. Each PODOS Pod is designed as a standardized 1 MW building block and designed for 128 GPUs, integrated and tested on the line so that site work reduces to preparing a pad and landing interfaces. Because the unit is a repeated product rather than a one-off structure, the route survey, lift plan, and interface drawing are reusable engineering — which is part of why PODOS targets a 90-day window from order to commissioning for a standard unit on a ready site.
That target assumes the constraints on this page are cleared, not ignored: a surveyed route, permits in hand, and a finished pad. If you are weighing this model against pouring a building, the factory-built versus site-built comparison sets out the tradeoffs; to size a configuration before a site visit, use the configurator; and any unfamiliar term here is defined in the AI infrastructure glossary.
The survey — not the lift — is where placement projects succeed or fail.
07
Steps, factory gate to interface sign-off
Stage 04 output
Every deliverable in this stage is a document before it is an event. Each one is produced, reviewed, and held on site before the transport moves.
Bridge ratings, overhead clearances, turning radii, weight-restricted roads and seasonal restrictions, recorded from the factory gate to the pad.
Transport configuration, tie-down and lift points, centre of gravity, and the trailer type the envelope demands.
Oversize and overweight movement permits per jurisdiction, plus pilot vehicles, police escorts, or curfew windows where required, with insurance certificates.
Published anchor locations, stub-up positions, and the heat-rejection clearance envelope the pad is built to, rather than improvised on the day.
A written plan with rated rigging, spreader geometry, mat sizing, the exclusion zone, and the wind limit that stops work.
Power terminated, heat-rejection and facility fluid interfaces made up and pressure-checked, fibre landed at the demarcation. The acceptance boundary between logistics and commissioning.
HONEST LIMITS
Factory-built infrastructure only wins where the finished machine can physically reach its position. These are the situations where it does not, and where a site-built approach or a different location is the more honest answer.
QUESTIONS
Usually yes, and always check before quoting a schedule. Under the Federal Highway Administration's commercial vehicle size and weight standards, width on the National Network is fixed at 102 inches and Interstate System weights are capped at 20,000 lb single axle, 34,000 lb tandem axle, and 80,000 lb gross, while vehicle height is left to the states. A factory-integrated data center unit typically exceeds at least one of those limits, so it moves under state-issued oversize or overweight permits — obtained separately in every jurisdiction the route crosses.
A level, load-rated pad with known bearing capacity and anchor provisions; conduit and service stub-ups terminated where the unit's interfaces will land; heat-rejection clearance; a network handoff point; and a route from the public road to the pad that carries the transport and crane loads. If any of those is unfinished, the unit is stored rather than set, at cost.
No. A mobile crane is the common method because it is fast when access allows, but self-propelled modular transporters, jack-and-slide systems, and roller sets place units where a crane cannot be positioned or where overhead clearance is limited. The method is chosen during the route survey, because it changes pad design, approach width, and ground preparation.
A relocatable unit is designed to be disconnected, lifted, and moved by reversing the placement sequence. The practical constraints are the same ones that applied on the way in: route, permits, crane access, and interface disconnection. Relocation is a logistics project, not a facility demolition.
Bring the access route, the pad drawing, and the interface positions. Sizing a configuration first makes the freight envelope a known quantity rather than a late surprise.